What's New

The County of Monmouth, with the cooperating agencies of NJTPA and NJDOT, has created this page to share information with the community and general public of the current progress on the CR537 West Main Street Corridor Roadway Improvements Project:

Project Status as of March 2022

Final Design Phase Work Effort (January 2020 – present)

On-Going Community Involvement & Public Outreach

  • Local Officials Meeting No. 1 – held February 2021
  • Community Stakeholders Meeting No. 1 – held September 2021
  • Right-of-Way (ROW) notification letters to affected property owners – mailed February 2022
  • Mailing of parcel maps and descriptions to affected property owners and scheduling of individual meetings with Monmouth County ROW representatives and appraisers – anticipated Spring to Fall 2022
  • Local Officials Meeting No. 2 – anticipated Spring 2022
  • Community Stakeholders Meeting No. 2 – anticipated Fall 2022
  • Public Information Center Meeting No. 1 – anticipated Spring 2023

On-Going Engineering and Environmental Items

  • Project Mapping & Field Survey – completed
  • Geotechnical Borings – completed
  • Environmental Permits & Approvals – in process
  • Right-of-Way (ROW) Negotiations & Acquisitions – in process
  • Conduct Utility Coordination – in process
  • Develop Engineering Technical Design Plans – in process
  • Draft Construction Staging Plans – in process
  • Complete Final Design Plans – anticipated Summer 2023

Recent News

Meeting summary for Community Stakeholders Meeting No. 1 is available to view
Read News
Right-of-Way (ROW) Acquisition Process Authorized to Proceed
Read News
Final Design Phase Community Stakeholder Meeting No. 1 was held on 9/17/21
Read News