Project Overview
| 1. Local Concept Development | 2. Local Preliminary Engineering | 3. Final Design/ROW Acquisition | 4. Construction |
|---|---|---|---|
| Purpose & Need Statement | Approved Design Exception Report | Construction Contract Documents & PS&E Package | Completed Construction |
| Data Collection & Environmental Screening Report | Cost Estimates (Final Design, ROW & Construction) | Environmental Reevaluations | As-Built |
| Selection of Preliminary Preferred Alternative | Approved Environmental Document | Environmental Permits | Update & Finalize Design Communications Report |
| Concept Development Report | Approved Project Plan | Acquisition of ROW | Close-out Documentation |
| NEPA Classification | Preliminary Engineering Report | Update Design Communications Report | |
| Create Design Communications Report | Update Design Communications Report | ||
| Initial Public Outreach & Involvement | Continued Public Outreach & Involvement | Continued Public Outreach & Involvement | Continued Public Outreach & Involvement |
Local Concept Development (LCD) Study Phase
The Local Concept Development Study was the first phase, conducted to identify need and propose extensive corridor roadway improvements. Monmouth County applied for the County Route 537 Corridor Roadway Study with the North Jersey Transportation Planning Authority (NJTPA) and NJTPA had oversight of the LCD study phase of the project.
During the LCD study phase, a Purpose and Need Statement was developed focusing on the need to improve safety and operational movements in the corridor. A number of sensible and practical conceptual alternatives were developed to meet the goals and objectives. Upon completion of an alternatives analysis, and in coordination with the local officials, community stakeholders, the general public, NJDOT, NJTPA and permitting agencies, a Preliminary Preferred Alternative (PPA) was recommended to address safety and traffic operational deficiencies with specific corridor roadway improvements. The proposed transportation improvements better accommodate pedestrians and bicyclists as well as vehicular traffic. The project limits were modified to eliminate the portion of the corridor within Freehold Borough due to lack of support from Freehold Borough for CR 537 roadway improvements within their jurisdiction. Resolutions of Support for the PPA were passed by the Township of Freehold on April 9, 2013 and November 12, 2013 and by the Monmouth County Board of Chosen Freeholders on November 14, 2013.
Additional Study information can be found in the Community Outreach Documents related to the LCD Study Phase of the project.
Local Preliminary Engineering (LPE) Phase
The LPE Phase involved performing engineering and environmental tasks required to obtain an approved National Environmental Policy Act (NEPA) document for the project. Right of Way and environmental impacts for the proposed project were identified along with the needed construction permits. Local officials meetings, a community stakeholders meeting, and a public information center meeting were also conducted during this phase for design development and environmental documentation completion. For the recommended refined PPA, the Township of Freehold passed a Resolution of Support.
Further LPE Phase project information can be found in the Community Outreach documents related to the LPE phase of the project.
Final Design (FD) Phase
The FD phase involves finalizing the roadway and intersection improvements and preparing the construction contract documents including design plans and specifications. Access modifications are completed in the FD phase along with acquisition of the necessary Right-of-Way (ROW) for construction of the project. The necessary environmental permits for construction will also be obtained during this phase. To inform and to encourage community input, three local officials’ meetings and a community stakeholders meeting were held. A public information center meeting will be held prior to the end of this phase.
The tasks to be conducted during the FD phase consist of, but are not limited to:
Further FD phase project information can be found in the Community Outreach documents related to the FD phase of the project.
Environmental Process
Monmouth County has jurisdiction of CR 537, however the project is funded by federal dollars. Any transportation projects receiving federal funding must also follow the National Environmental Policy Act (NEPA) process.
The New Jersey Department of Transportation (NJDOT) Bureau of Environmental Resources (BEPR) oversees this aspect of the project in cooperation with Monmouth County and NJTPA. They coordinate with the permitting agencies, such as NJDEP and NJSHPO (New Jersey State Historic Preservation Office), to develop a cohesive plan for proposed improvements. The agencies look carefully at comments from the public, therefore community involvement is an important part of the environmental process and moving the project forward with consensus and environmental compliance.
The LCD study phase required the identification of any environmental concerns and to develop an environmental profile. When analyzing alternatives, the Project Team looked to avoid or minimize environmental impacts and, if that was not possible, then to provide mitigation. The environmental resources include air, noise, hazardous or contaminated sites, parks, wetlands, water resources, social and economic impacts, and cultural resources such as historic structures and facilities.
During the LPE phase environmental and cultural resource studies were continued. The results of the environmental screening and cultural resource studies, which are part of the project schedule, were presented at the public meetings. Environmental mitigation and permitting are part of the FD phase.
Community Involvement
Monmouth County and the cooperating agencies of NJDOT and NJTPA, are committed to developing transportation improvements that best balance transportation needs, the environment, community concerns and cost. As part of the Community Outreach effort, meetings have been and will continue to be held with local officials, community stakeholders, and the general public to share project information and to obtain input and broad-based support for corridor roadway improvements. Community involvement is on-going and an integral part of all phases of the project, including the Construction phase.
Project Funding
NJTPA had project oversight for the LCD study phase using federal funds and has developed flowcharts that show all the project phases and the steps to complete for each phase of a transportation improvement project. Once the Preliminary Preferred Alternative (PPA) for corridor roadway improvements had been determined, with resolution of support by the Freehold Township and Monmouth County Board of Commissioners, the NJDOT Local Aid Department then assumed administration of the project with Monmouth County as the lead for the project, utilizing federal funding for the LPE phase, FD phase and future Construction phase.
Monmouth County and NJDOT Local Aid, together with the cooperating state and federal agencies, have continued to move the project forward using federal funding. They will do so for the Construction phase as well, as federal funding is made available.
Project Schedule (Phases)
|
Local Concept Development (LCD) Phase 551_e5e856-4d> |
2011 – 2014 completed 551_2ee04c-d9> |
|
Local Preliminary Engineering (LPE) Phase 551_8c9290-72> |
2015 – 2019 completed 551_37e0b1-18> |
|
Final Design (FD) Phase 551_20eee6-8c> |
2020 – 2026 551_866c7d-59> |
|
Construction Phase 551_890a65-18> |
2026 – 2028 551_baec92-e4> |
Final Design Phase – Project Schedule (Major Milestones)
|
Environmental Permits 551_e4f363-5e> |
Spring 2021/Spring 2026 551_68a155-0f> |
|
ROW Availability / Easements 551_5bc820-cd> |
Fall 2025/Winter 2026 551_a0dbd4-ce> |
|
PS&E Plans 551_9ae1ca-c0> |
Spring 2026 551_d4dbc0-dc> |
|
Completion of Final Design Phase 551_a59c9b-c3> |
Summer 2026 551_bf1d8f-54> |
Final Design Phase – Anticipated Community Involvement Schedule
|
Local Officials Meetings No. 1 and No. 2 551_28c1b3-ae> |
February 2021, June 2023, August 2025 551_fa78b6-c4> |
|
Community Stakeholders Meetings No. 1 and No. 2 551_91c13e-07> |
September 2021 551_12e1b7-c1> |
|
Public Information Center Meeting 551_04ca78-89> |
February 2026 551_187055-b7> |

