Project Schedule
The County of Monmouth, with the cooperating agencies of NJTPA and NJDOT, will provide updates in an effort to keep the community and general public informed of current progress on the County Route 537 West Main Street corridor roadway improvements project.
Project Schedule (Phases)
Local Concept Development (LCD) Phase |
2011 – 2014 completed |
Local Preliminary Engineering (LPE) Phase |
2015 – 2019 completed |
Final Design (FD) Phase |
2020 – 2026 |
Construction Phase |
2026 – 2028 |
Final Design Phase – Project Schedule (Major Milestones)
Environmental Permits |
Spring 2021 |
ROW Availability / Easements |
Summer 2025 |
PS&E Plans |
Spring 2026 |
Completion of Final Design Phase |
Spring 2026 |
Final Design Phase – Anticipated Community Involvement Schedule
Local Officials Meetings No. 1, No. 2, and No. 3 |
February 2021, June 2023, August 2025 |
Community Stakeholders Meeting No. 1 |
September 2021 |
Public Information Center (PIC) Meeting |
February 2026 |