MONMOUTH COUNTY

County Route 537 (CR 537)

West Main Street Corridor Improvements

Between Sentinel Road and U.S. Route 9 Interchange

Freehold Township

Project Schedule

The County of Monmouth, with the cooperating agencies of NJTPA and NJDOT, will provide updates in an effort to keep the community and general public informed of current progress on the County Route 537 West Main Street corridor roadway improvements project.

Local Concept Development (LCD) Phase2011 – 2014 completed
Local Preliminary Engineering (LPE) Phase2015 – 2019 completed
Final Design (FD) Phase2020 – 2026
Construction Phase2026 – 2028
Environmental PermitsSpring 2021/Spring 2026
ROW Availability / EasementsFall 2025/Winter 2026
PS&E PlansSpring 2026
Completion of Final Design PhaseSpring 2026
Local Officials Meetings No. 1, No. 2, and No. 3February 2021, June 2023, August 2025
Community Stakeholders Meeting No. 1September 2021
Public Information Center (PIC) MeetingFebruary 2026

Do you have a comment or suggestion?  Are you a new resident or business owner in the area of the project? Feel free to contact us and use the online comment form for questions or comments or to be added to the contact mailing list.