Project Schedule

The County of Monmouth, with the cooperating agencies of NJTPA and NJDOT, will provide updates in an effort to keep the community and general public informed of current progress on the County Route 537 West Main Street corridor roadway improvements project.

Project Schedule (Phases)

Local Concept Development (LCD) Phase 2011 – 2014 completed
Local Preliminary Engineering (LPE) Phase 2015 – 2019 completed
Final Design (FD) Phase 2020 – 2026
Construction Phase 2026 – 2028

Final Design Phase – Project Schedule (Major Milestones)

Environmental Permits Spring 2021
ROW Availability / Easements Summer 2025
PS&E Plans Spring 2026
Completion of Final Design Phase Spring 2026

Final Design Phase  – Anticipated Community Involvement Schedule

Local Officials Meetings No. 1, No. 2, and No. 3 February 2021, June 2023, August 2025
Community Stakeholders Meeting No. 1 September 2021
Public Information Center (PIC) Meeting February 2026

Do you have a comment or suggestion?  Are you a new resident or business owner in the area of the project? Feel free to contact us and use the online comment form for questions or comments or to be added to the contact mailing list.